Error while converting planned order to process order

Aug 27, 2017 at 03:27 PM

56

avatar image
Former Member

error-screen-shot.jpgHi

Please help me to resolve below issue-

The existing issue is in S4 HANA Release 1610. While converting planned order to process order, the system shows the error as enclosed.

Error - Production Version required - Planned Order xxx will not be converted.

PV has been defined for material and necessity config. also has been done for BOM explosion.

Please let me know if I have missed any configuration setting.

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

2 Answers

avatar image
Former Member Dec 26, 2017 at 11:21 AM
0

Hi Nitesh,

Please check the Prod. Version Validity date's as well as Plnd Order Start Date and End Date.

Thanks,

Share
10 |10000 characters needed characters left characters exceeded
Jessica Li
Mar 23 at 08:47 AM
0

Hi Nitesh,

Please check if production version is set in planned order. See attached screenshot for the filed.

If not, how the planned order is created, by MRP?

planned-order-production-version.pngbest regards,

Jessica