Skip to Content

Error while converting planned order to process order

error-screen-shot.jpgHi

Please help me to resolve below issue-

The existing issue is in S4 HANA Release 1610. While converting planned order to process order, the system shows the error as enclosed.

Error - Production Version required - Planned Order xxx will not be converted.

PV has been defined for material and necessity config. also has been done for BOM explosion.

Please let me know if I have missed any configuration setting.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • avatar image
    Former Member
    Dec 26, 2017 at 11:21 AM

    Hi Nitesh,

    Please check the Prod. Version Validity date's as well as Plnd Order Start Date and End Date.

    Thanks,

    Add comment
    10|10000 characters needed characters exceeded

  • Mar 23 at 08:47 AM

    Hi Nitesh,

    Please check if production version is set in planned order. See attached screenshot for the filed.

    If not, how the planned order is created, by MRP?

    planned-order-production-version.pngbest regards,

    Jessica

    Add comment
    10|10000 characters needed characters exceeded

  • Sep 28 at 04:55 AM

    Hello ,

    As per S/4 HANA system, Production Version is mandatory. please check the validaity incase PV available if not , please create a new one.

    Thanks.

    Kumar semmalai