Please help me to resolve below issue-
The existing issue is in S4 HANA Release 1610. While converting planned order to process order, the system shows the error as enclosed.
Error - Production Version required - Planned Order xxx will not be converted.
PV has been defined for material and necessity config. also has been done for BOM explosion.
Please let me know if I have missed any configuration setting.
Hello ,
As per S/4 HANA system, Production Version is mandatory. please check the validaity incase PV available if not , please create a new one.
Thanks.
Kumar semmalai
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Nitesh,
Please check if production version is set in planned order. See attached screenshot for the filed.
If not, how the planned order is created, by MRP?
planned-order-production-version.pngbest regards,
Jessica
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Nitesh,
Please check the Prod. Version Validity date's as well as Plnd Order Start Date and End Date.
Thanks,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.