Hi friends,

We are trying to replace a bom component with a new from a future date using ECR. we changed the material master MRP2 view with indicator and future component and effective date. How to change the bom with ECR. do we need to delete the existing component. we are trying to use t code CC01. but not clear. can anybody answers, how exactly we have to proceed.

Thanks in advance

venkat

Add a comment
10|10000 characters needed characters exceeded

Related questions

4 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Sep 11, 2007 at 04:00 AM

    Hi Venkat

    U can create a EC# where changes to BOM are allowed and then goto transaction CS02.In the initial screen enter the change number and then make necessarry changes to the BOM components.U can put deletion indicator to the previous component and add a new component with this change number.

    Thanks

    Ranojoy

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Sep 11, 2007 at 04:15 AM

    HI Venkata,

    goto CC01 , press enter it wil take you to valid from date, give valid from date and give text to change number and status information "01" press enter

    check BOM actv and object and even for material ok save it , note change number

    then goto CC11 , give that material and assign this change number

    goto CS02 and give the material and change number and valid from date do the changes in the component ,

    Thanks

    Bala

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Sep 11, 2007 at 04:35 AM

    Hi,

    Create a change number in CC01 and select object type, Object types you add the BOM and select the BOM in Objects. Enable the Activ, Mgt Rec,Onje and Gendial indicators.

    Now go to CS02, enter the Change number and delete the component and do changes as you need.

    Thanks and regards

    Murugesan

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Sep 11, 2007 at 08:10 AM

    what are the repeated regular issue that come in the sap pp support project

    thanks in advance

    v.raj

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.