In WEBI -cumulative sum based on the week number

0 Kudos

My requirement is

Have different weeks based on the customer...

calendar weeks ( starts from week 1 to week 52) but other customer week is starting from 40th week ...this start week will vary every year .

Need to calculate the cumulative sum from week1 to all the week in that year.

I can use the RunningSum( ) if the week is starting from 1 to 51 ...hear I can't because the week one is not the first week. Its week 40th.

Experts please suggest me how can I achieve my results.

Accepted Solutions (0)