Guys!

I've tried to search for help on this topic, but not found all that I need. So now it's time to ask the question to you. Hopefully someone has done this already, and has all the answers.

So; Over time we have developed a solution in our SAP system. All objects are kept in the same development class. Now the company is being splitted, and my task is to move this custom solution to a new SAP system.

I've found some help at SAP: Change and Transport System - Overview (BC-CTS) -> Transports of Copies and Relocations

From what I can read, I should select "Relocations with development class change"

Here I read:

"You can use this request type when you want to change the development system of a

complete development class on a permanent basis."

This is exactly what I want! (I think?)

So I head over to the original system (dev), start transaction SE80 and select the correct Development Class. I right click on it and select "Write transport request".

Here I get the question: "Do you want to transport the development class or all of the objects in the development class ?".

I would rather like to take the whole dev. class.

Now I get into trouble: I create a new transport req of type "Relocation of objects with dev. class change". The next dialog box is asking for "Target dev. class". But this information isn't available.

Something I do is wrong, but what? How should I perform this "easy" task?