HI

I created In (INQUIERY) and I save the IN. (I MAINTAINED PRICINGIN IN)

WITH REF TO IN IAM CREATING QT SYSTEM IS NOT COPYING PRICING

In -


>QT

WHERE I MISSED THE SETTING’S

murli

Accepted Solutions (0)

Answers (7)

Answers (7)

Former Member
0 Kudos

Hi

Folowing need to be checked

1) Pricing procedure determinnation T.code OVKK(sales area should beassigned with your your pricing procedure.In the mean time check your customer pricing procedure in customer master as well as document pricing procedure in sales doc type through t code vov8.

2)Item cateogory through transaction VOV7 check the field pricing which should be X.

3)check copy control

hope this will solve your error.

Regards

Biswanath

Former Member
0 Kudos

Hi,

Check your Copycontrols.

Go go VTAA, for the combination of IN to QT, select AFN item category, in pricing type field, u can choose of your choice. To copy pricing elements.

Regards,

Ramesh

Former Member
0 Kudos

Hi,

Check with ur requirement. Whether do u want the same pricing procedure or different one?

This is cpntrolled through Copycontrols.

Go go VTAA, for the combination of IN to QT, select item data, in pricing type field, choose ur options.

U just check there....U vl get the clear idea.

Regards,

Praveen.

0 Kudos

Hi,

Check the copy controls from document to document. and assinged ur pricing procedure to the combination of SALES AREA+ CPP + DPP.

And if you have copied from previous document. all the setting for copy controls will get copied. and if you have defined newly the document type for IN & QT you also have to do the copy controls for document to document.

regards

preetham

Former Member
0 Kudos

Hi,

Also check the item category proposed during QT and it's settings in VOV7.

Reward if proves helpful

Regards

SD

Former Member
0 Kudos

Check the copy contorls in VTAA

Former Member
0 Kudos

Check for copy control also check for pricing procedure assignment