capacity

Former Member
0 Kudos

HI FRIENDS,

although i have assigned capacity catagory 001 to the W.C.and ,also the indicator as finite sheduling .when i go for capacity availability check in production order, i am getting this error message : No reqmts/caps exists or not relevant to finite scheduling

and the diagosis is coming like this.

Message no. CY298

Diagnosis

In the capacity availability check either no capacities were found or none were found that were relevant for finite scheduling or no capacity requirements were found.

The possible causes are:

no capacities have been assigned to the work centers checked

in the capacities at the work centers checked the indicator Relevant to finite scheduling is not set. Thus the capacities can have an unlimited load.

no capacity requirements exist for the order checked

System Response

The capacity availability is checked.

Procedure

Assign capacities to the work centers affected by the order.

Set the indicator Relevant to finite scheduling at the capacities in the work centers affected.

Find out why no capacity requirements exist and, if possible, solve the problem.

Carry out the capacity availability check again.

I HAVE CHECKED EVERY THING IS O.K , STILL THIS ERROR PERSISTS.

PLEASE SUGGEST.

Thanks& Regards

omkar

Accepted Solutions (0)

Answers (5)

Answers (5)

former_member698542
Active Contributor
0 Kudos

Hi,

In CR02 change work center please activate the indicator Relevant for finite scheduling in Capacity header in Work center capacity view.

In transaction OPU3 Scheduling parameters check Generate capacity requirements activated.

In transactiob OPJK - Order control check capacity availability check activated in the capacity availability tab. Maintain a overall profile tehre.

Hope the above solve your problem.

Thanks and regards

Murugesan

Former Member
0 Kudos

Hi Omkar,

Check for CR02 in that capacity header, see if its check for finite scheduling

Thanks

Bala

Former Member
0 Kudos

Hi,

check in opu3 whether generate capacity indicator is enabled or not for your order types.

Regards,

nandha

Former Member
0 Kudos

Hi Omkar,

In CR02,

in capacity header screen, please check shift sequences are maintained.

IMPORTANT THING is check the validity of the shift you have defined.

Regards

Ranga

Former Member
0 Kudos

hi ranga ,

here i have maintained no shift sequence .although i have 4 shifts A B .C&G .So please guide me how i will maintain that and calculate the capacity of work center.

Thanks and regards

omkar

Former Member
0 Kudos

hi,

Check the Control key which is assigned to operation in Routing In that whether Scheduling and Det.capacity Requirements indicators both are selected or not. if not then select the both.

Hope it wil help you

Former Member
0 Kudos

hi omkar ,

have u maintained the capacity category that has to be scheduled in scheduling tab page .the capacities that r define in scheduling tab page of work centre are relevant for scheduling.so please check for the same thing .a;so please do check details of the control key ,wether the scheduling is activated for that workcentre through control key .

1) check control key details

2) check for entry in scheduling tab page in workcentre

please check and revert back