Hi all,

We have got a route scheduling problem. We have defined route schedules for Dec 27th and 28th for our customers. Due to heavy workload in the warehouse we need to work on Dec 26th as well. As this is normally a holiday we removed Dec 26th from the holiday calendar. Now the factory calendar says that Dec 26th is a normal working day. We also created a route schedule entry for Dec 26th.

When creating an order for Dec 26th, we still don't get the route schedule. The system don't complain about holidays so the calendar change works fine.

If we set the delivery date for Dec 27th it works fine.

Are there some other calendar or settings we need to check?

best regards,

Glenn Karlsson