We are implementing PPDS on SAP S4 Hana 1610.

We are using alternate resource functionality.

We are outsourcing the operations if in house capacity is not available on main resource and on alternate resource.

When user is creating the Subcontracting Purchase order, user wants alters regarding the capacity availability on resources.

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

avatar image
Former Member Sep 07, 2017 at 02:47 AM
0

Check Heuristics SAP_MULT_SCH in DS planning board , system shall propose alt resources