Skip to Content
avatar image
Former Member

reverse PGI despite GR is not cancelled - STO

Hi,

An interressing question was raised on an other SAP forum and we failed to find the answer.

In case of STO:
1. PO (ME23N)
2. Delivery with reference to PO (VL10B)
3. Picking (VL02N)
4. PGI (VL02N)
5. GR with reference to outbound delivery (MIGO)

After that it is possible to reverse the PGI even though GR is done and hasn't been cancelled.
My question is whether it is the normal. I would expect SAP not to allow VL09 (reverse of PGI) if GR isn't reversed. (Stock in transit goes into negative in MB5T report)

Or maybe there's a need for plants to be able to influence their processes and that's why it is allowed.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

0 Answers