Skip to Content
avatar image
Former Member

Procurement lead time consideration for Production planning start

Hi,

I have updated the Procurement lead time for Raw material is Two days in Planned Deliv. time column under the MRP2 View tab.

My requirement quantity is 5000 for the FG Part number. Based on my routing and available capacity, it will required 5 days to complete the production after Receipt of Raw material.

But after executing MRP run, system release the PR for Raw material and the release date as 28.08.2017 & Delivery date is 30.08.2017.

For FG part, system display the Start date as 28.08.2017 and the End date is 04.09.2017.

Actually after receipt of Raw material only i can able to start the Production activity. So the Raw material Receipt date is 30.08.2017 or next day, but here the Start date is today.

Request your valuable suggestion to correct the error.

Regards

R Vaithiyanathan

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

0 Answers