IF we have 10 InfoPackages and if we need to create an InfoPackage Group for 7 of them, How do we do it??

Plz provide a detailed Step-by-Step procedure for the same/ create an InfoPackage group!!

Ur help is really appreciated!!

Thanks & Regards,

Sapster.

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Sep 06, 2007 at 12:48 PM

    InfoPackage Groups are obsolete technology. You can achieve the same goal using Process Chains with much better monitoring, scheduling, and overall design flexibility.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Sep 06, 2007 at 12:45 PM

    Hi sapster.

    Open RSA1 -> Modeling -> InfoSources -> Show InfoPackage Groups -> Right click on "InfoPackage Groups" -> Create... -> Drag and drop the 7 InfoPackages -> Right click on the InfoPackage Group that you just created -> Schedule -> Check that all InfoPackages are selected -> Schedule the job just as you normally do with a InfoPackage.

    [edit] SAP recommends that you use process chains, and InfoPackage Groups are no longer supported from BI 7.0.

    Hope it helps.

    BR

    Stefan

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hello Stefan,

      Thanks for ur response...with ur detailed steps..really helpful.

      While sheduling at the last ..by clicking the context menu of our created IP Group.. I am not getting any screen to schedule the same..(I am getting amessage at the mottom saying its not possible to run it in the back ground for my client workstation or similar to this)

      Could u plz let me know.. what it looks like for these remaining steps

      "Right click on the InfoPackage Group that you just created -> Schedule -> Check that all InfoPackages are selected -> Schedule the job just as you normally do with a InfoPackage."... thansk again.. assigend points...

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.