Hi ,

We recently upgraded PPM 6.1 system to SP08 level from SP04 level.

Now, during post upgrade testing we found that cproject tabs are blank (means there are no fields appearing under those tabs)

Screen shot attached.

Please suggest what went wrong here.

sp-test.png

Thanks

Saurabh

sp-test.png (31.7 kB)
Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

5 Answers

  • Aug 23, 2017 at 02:52 PM

    Hello Saurabh,

    The observed behaviour is caused by a bug. You can resolve this by implementing correction note Nr. 2500389. You can alternatively refer to Knowledge Base Article Nr. 2500123 if for some reason you cannot implement the correction note straight away.

    Best regards

    Francesco

    Add comment
    10|10000 characters needed characters exceeded

  • Aug 23, 2017 at 04:02 PM

    Thank you very much for quick response Francsco.

    Its always Nice to see your reply :)

    Will check these note and come back here.

    Thanks You...

    Add comment
    10|10000 characters needed characters exceeded

  • Aug 23, 2017 at 04:13 PM

    Hello Francesco,

    Referring KBA 2500123, I was trying to activate master switch "an entry with Area "0006", Name "0028" and Settings Value "X""

    But I am unable to insert this entry due to following error:

    (please see attached) spro-cust.png

    Please suggest how to insert this value.

    Thanks

    Saurabh

    Add comment
    10|10000 characters needed characters exceeded

    • Hello Saurabh,

      The long text of the error message /RPM/PLANNING432 you are getting is:

      *********************
      You cannot activate the fiscal year switch
      Diagnosis
      You wanted to activate the 0010 Portfolio Item FI/CO Planning and Integration -> 0006 Fiscal Year Switch (see SAP Note 1457426).
      Procedure
      You can activate the 0010 Portfolio Item FI/CO Planning and Integration -> 0006 Fiscal Year Switch (see SAP Note 1457426) only if you have activated the 0002 Master Switch -> 0008 Enhanced Capital and Resource Mgmt Switch (see SAP Note 1457426).

      *********************

      The error message is related to other switch 0010/0006. Have you also changed the value of this switch? or was it already 'X' (in which case, have you removed an existing entry for switch 0002/0008)?

      I assume that it should be possible to avoid the error message by following the information in the above long text.

      Best regards

      Francesco

  • Aug 28, 2017 at 10:47 AM

    Hi Francesco,

    I followed the long text instructions but the issue is 'system is not allowing me to insert that entry (0002/0008) in override default global settings"

    How can I insert this entry? :(

    Thanks.

    Add comment
    10|10000 characters needed characters exceeded

  • Feb 07 at 08:42 PM

    Hello Saurabh,

    Were you able to address this issue?. We had a same issue with SP08 then we installed SP09 which has a fix for blank screens. I hope this helps.

    Mohan