Routing vs work scheduling

50 Views

Hi Sir/Mdm,

Example: Under Routing CA03 - There are 1 operation namely Assembly 1 with labour time of 0.4 hours to produce 1 part. To produce 10 parts, I will require 0.4x10 = 40 hours. If I have two Assembly 1 station and to produce the same 10 parts, I will only require 20 hours. How can I reflect the additional work station capacity in the routing or work scheduling?