What are the configuration required to automatically get the activities in the confirmation screen(COR6N), I am having problem executing this. The activities are not getting populated with the values, however the units of measurement is getting populated on the basis of parameters maintained for the standard value defined in the work center.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Aug 25, 2017 at 11:51 AM

    Hi Arpit Kumar,


    During the execution of the Transaction Code : COR6N, on the top, you have the option of Actual data Button
    Once you enter the Process Order Number & the Phase, Click on Actual data, then System will pull the data Automatically
    Please find the attached screen shot of the same

    If you want to look at the Configuration settings, for this screen, you can use the Transaction Code : OPK1
    Here you can choose the required options & can test the view, by the Click on Preview button.
    Please find the attached screen shot for the same

    Hope, this will be of useful info. Thanks & Regards : Raja S Reddy

    Add comment
    10|10000 characters needed characters exceeded

    • Dear Raja S Reddy

      The thing is my client doesn't wants activity type to be maintained as costing is not required, but they want to see the values to be populated for the Std. parameter key maintained. How to handle this situation?