How do I turn on reorder point planning for multiple storage locations? I thought this was at the bottom of MRP4 tab, but there's nothing there.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Aug 24, 2017 at 07:24 PM

    Planning is usually at plant level.

    If you want plan storage locations individually or exclude from planning then you will only see this field in MRP4 view if you have entered the storage location in the organization data when you go into the material master.

    In MMSC transaction it is more convenient to maintain the indicator than individually per storage location in MM02.