S4 HANA 1610 how to update product in planning version 000 in PP/DS

Hi experts:

I need to update the location-product in /sapapo/mat1, but as you can see below, none of the fileds are editable ..

How can I change the product in planning version 000 ?

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    Sep 07, 2017 at 02:49 AM

    In S4 HANA , The Product master cannot be changed on these fields , you have to maintain Material master - MM02 , there is a advanced planning view in Mat Master , there these fields can be edited and it gets populated over to Prod. master