I have created PR with 2 line items with same material and vendor. both account assignment category K cost center.

In ME59N i put pr no and click on Generate Schedule lines.

Then execute

Po is created, it is coming in 2 lines. But i want it in one line. Means quantity of materials of both line added and delivery date of 1st line item shows. In delivery scedules shows another delivery date of 2nd line item.

Plz answer.

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

2 Answers

Jürgen L
Aug 23, 2017 at 07:45 PM

Account assignment information is not at schedule line, it is per PO item.

With K Cost Center you can potentially have different cost centers per item, while items without account assignment are just going to stock and follow the rules of automatic account determination, hence they can be combined.

See the F1 field help on the field "create schedule lines" , it is explicitely referring to non-account assigned requisitions.

10 |10000 characters needed characters left characters exceeded
Amiya Shankar Mahanta Aug 23, 2017 at 04:06 PM

If i m not giving K cost center , then it is possible in normal case.

Plz help

Show 1 Share
10 |10000 characters needed characters left characters exceeded

Hello ,

I believe the delivery date should be same for both Pr and the requitement type should be collective in material.