Skip to Content

APO - setup scheduling in PP/DS

Hi gurus, i need suggestion how to manage this process.

A single operator perform the setup on different machine in the shopfloor. Each machine is a resource in APO (and a WC in ECC). This is a constraint because, being only one person, the setup on different machine cannot overlap.

The second constraint is that, on the same resource, there are setup optimization logic based on the raw material used for production. This is archived using the setup matrix.

I'd like a suggestion to manage this process. The setup on different resources cannot overlap due the first constraint, and i have to run the setup optimization (optimizer available in APO) on the single resource.

Thanks.

M.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Aug 28, 2017 at 09:40 AM

    any suggestion?

    thanks

    Add comment
    10|10000 characters needed characters exceeded