Scheduling of planned orders in PPDS

ramtoc
Explorer
0 Kudos

We are implementing PPDS on S4 Hana 1610.

We are mapping the process of heat treatment in our foundry.For heat treatment process which is mapped on routing we need to group the planned orders as per the gross weight and MOC (material group), heat treatment uses the resource which has capacity 1000kg thus before starting heat treatment we need to group the orders as per MOC and gross weight. We should have the planned orders (which are may be in future) for a particular product or MOC and system should be able to group the orders together and schedule them.

Accepted Solutions (0)

Answers (0)