Hello all

I would like to change the posting date while posting the stock from quality inspection to unrestricted. Is there anyway, i can do that?

thanks & regards

Krishna

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Sep 07, 2007 at 12:49 AM

    Kishnamohan,

    I'm sorry .Actually you can change the start date.I just tested this one.When you go to QA32 click inspection lot and change the date in the inspection lot.The end date reamins the same and does not update .When you click the check mark the syustems gives a warning that the end date is not consistitent or something like that.But that is just a warning.So the start date can be changed .Let us all know on how ur doing on this one.Thanks

    naik

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      Thanks all for your responses. I think when you have handling units in your quality inspection lot,system will not allow you to change the posting date. I could not solve the problem. but for now, we opened the current period and adjusting the stock accordingly.

      Regards

      Krishna

  • Posted on Sep 04, 2007 at 07:30 AM

    Dear Mr.Krishnamohan,

    I dont know how to carryout in QA12,but try with this.

    IF you want to Change the starting & End date,please check as given below.

    1.Using T code QA32,give the inputs and execute,

    2.Select the inspection lot row & click on the Change Inspection Lot button

    (ControlShiftF6).

    3.There you can change the Insp.Start Date & End Date.

    Regards

    Mangal

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Sep 07, 2007 at 12:19 AM

    Krishnamohan,

    First of all i'm not sure ion why you wnat to change the posting date .The start date and end date is populate based upon the avg.duration field you input in MM -QM view .The start date is populated when the process order is released and based on the value given in material master the system calculates the end date.you can try changing it in in QA32 but i'm sure i woudlnt change .Your are asking the system to calculate the end date by giving a value in Material master and once it's calculated now you want to change the date .As per i know this may not be possibleunless there is someone who has done this before.

    Experts pls guide if i'm wrong in saying so .Thanks

    Naik

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.