Skip to Content
0
Former Member
Sep 03, 2007 at 04:27 AM

Planning Time Fence

29 Views

Hi All,

I have a FERT for which one ROH, The lead time for the ROH is 60 Days and my client wants to firm it so the planning time fence is also for 60 days.

When I create a requirement for FERT text month,then planned order for ROH is lying after 60 days (PTF) Practically it is not possible on the shop floor because without ROH how to start production of FERT, so can any tell me how to handle this situation.

Sekhar