Profit Center Substitution in GGB1 for BSEG in MB1B

Hi,

After using T Code: MB1B and movement type : 413 E

The only prerequisite that i have maintained is as follows:-

SYST-TCODE = 'MB1B'

The profit centers in the Debit & Credit are picked based on the master data of the material.

I have provided a constant value in the assignment field and profit center.substitute.pngcapture.png

As you can see in the screenshots, the substitution is working for Assignment field, but it is not working for profit centers.

I am assuming that the system is taking priority of the master data over the substitution.

Is there a way in which the substitution would take a higher priority.

Regards,

Gavin Monteiro.

substitute.png (16.6 kB)
capture.png (11.0 kB)
Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Aug 23, 2017 at 09:32 AM

    Hi,

    Have a look at this OSS note:

    644682 - MB1B: Manually entered Profit Center is not saved

    Regards,

    Eli

    P.S. For general logic of Profit centre determination in such cases, consult OSS note

    978159 - Problem with profit center determination