on 09-01-2007 9:50 AM
Hi
I have maintained the setting overall profile SAPSFCG013 in txn OPJK and indicator release order "3" , when i create more and more order for the same date still system says capacity is available... I have maintained all settings for capacity ( like control keys and "generate capacity" in scheduling parameters ) ..... can anybody help
VijayaBhaskar
Hi Prashob , Yes the indicator is set and also in CM01 i could see the overload.... is there any setting missing to stop the release of order?
Prasanna ( writting on behalf of vijay )
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Vijayabhaskar,
Is your workcenter defined for "Finite Scheduling"..check this in the capacity header of the workcenter.
Regards,
Prasobh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Whenever you create and release the production order, you need to assign/dispatch the order to that work centre
please go through the help url
http://help.sap.com/saphelp_47x200/helpdata/en/1a/f2f33419ec8d44e10000009b38f844/frameset.htm
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
You need to allocate your capacity in CM25.
Let me know where the system says capacity is available?
Regards
Ranga
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
7 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.