Hi,

I have problem using counting class.

Currently I have to create new working time that starts from 8:30am to 1:00pm(to be considered 1 working day). Hence these are the steps taken:

Step1: Time Management->Time Data and Recording Administration->Absence->Absence Counting->Rules for Absence counting(new)->Define rules for rounding counted absences.

Lower limit Upper limit Target value

Z5 001 0.55600 0.50000

Z5 002 0.55700 1.00000

Step2: Define counting rules.

For annual leave, will have many counting rules, hence I added one more, whereby I indicated the rounding rules is Z5. And introduced a new counting class 4. But at payroll simulation, encountered issues.

But If I set the counting class to 1 and rounding rules Z5, it did not calculate the half day according to Z5 rounding rules. Whereby counting class 1 is already being use by our other rounding rules which is different from Z5.

Please advise how to use counting class? and is counting class used in the payroll schema.

Best Regards,

Grace