issue management

Presently we are working on issue management solman 4.0 with sp10

Could any one help me in knowing if I have to customize the issue from slfi to zslf .

Kindly let mail me back if u need any more details

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Sep 04, 2007 at 04:33 AM

    dear sidd,

    Issue mgmt is same like SLFN/ SLF1 transaction. So copy the standard t.type SLFI to your ZSLF. Then do as usual partner det procedure, Access seq, etc

    Regards

    senthil

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Thanx senthil for the response,