hi gurus
my question is when am doing route determination . In sales order it is automatically not coming what could be the reason. I did all the configuration settings and am doing in the country india not country DE. So it is not coming automatically. please help me out in this regard
thanksin advance
well these are few steps for proper route determination if you have maintained it should work.
route determination is used by the system if there is exactly one route schedule defined for a particular combination of requirements.you can define several routes for each combination of requirement
The system determines the route with the earliest delivery time at the ship to party ( this is for deliveries without a preceeding document)
for deliveries based on preceeding documents system searches route nearest to the planned date/time of delivery. the folowing search algorithm is used.
1. If there exists a route schedule for a specified time then system assigns it to delivery.
2. if there does not exist a rouote schedule for a specified tiem specified then system searcehs for the previous route schedule up to the GI time
3. the system searches for next route schedule in future and assigns this to delivery if step 2 is not planned.
Also check your assignments in route determination in SPRO ..
Hope this fixes your problem
Cheers
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
90 | |
8 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.