Hi All
Is there any provision / setting available wherein the quanitities of Demand Management could be splitted into quantities as per my production capacity / limit and that too on successive days?
Eg: Say there is a requirment of 1000 pc on 35th weeek & i want that after MRP run; system should propose planned orders as below (because my production line constraint is 300 pieces only)
Planned Order 1 300 27th Aug
Planned Order 2 300 28th Aug
Planned Order 3 300 29th Aug
Planned Order 4 100 30th Aug
I tried this by using split indicator in MD62; but it only splits the quantity..........Provision of lot size (MRP 1) restricts the quantities to 300 pieces only but proposes planned orders on the same day as of requirment
Please suggest how to define such setting which shall automatically generate planned orders based on capacity constranit