Hi All

Is there any provision / setting available wherein the quanitities of Demand Management could be splitted into quantities as per my production capacity / limit and that too on successive days?

Eg: Say there is a requirment of 1000 pc on 35th weeek & i want that after MRP run; system should propose planned orders as below (because my production line constraint is 300 pieces only)

Planned Order 1 300 27th Aug

Planned Order 2 300 28th Aug

Planned Order 3 300 29th Aug

Planned Order 4 100 30th Aug

I tried this by using split indicator in MD62; but it only splits the quantity..........Provision of lot size (MRP 1) restricts the quantities to 300 pieces only but proposes planned orders on the same day as of requirment

Please suggest how to define such setting which shall automatically generate planned orders based on capacity constranit

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Vicky

Try using daily lot size TB & Maximum lot size as 300, so that only 1 planned order is made with lot size 300 per day.

Regards

Prasad

Reward if useful

former_member184655
Active Contributor
0 Kudos

Hi,

Check with this procedure.

Using T code - OMI4 - Lot Size Definition.

1.Use the lot size FS - Fixing & Splitting.

2.Set the indicator last lot to exact.

3.Set the overlapping indicator as "-"

4.Enter the Rounding value as say any numeric value

5.In material master MRP 1 VIEW set the lot size as FS.

6.Enter the takt time as 1 day if you want daily planned order .

Check with this & revert

Regards

Mangal

Former Member
0 Kudos

Hi,

Many thanks for your valuable feedback....using this planned order could be splitted into no of days....

but why we need to keep in lot size procedure and lot size indicator as "S" only. i.e. static......

can u explain me its significance?