cancel
Showing results for 
Search instead for 
Did you mean: 

how to scheduling on one work center but three tasks?

Former Member
0 Kudos

herein I assume I have a work center and can start run three work orders at the same time

the capacity of work center is 24h(three workers 3x8=24h)

the work hours for a part is 16h(capacity calculated by the hours of routing)

I want to get the result as following:

if sales needs one part(relevant to this order),then sap will tell me two days ahead should open a order(16/8=2day),because even three workers work on it,it still not speed up the process.

if sales needs two parts(relevant to this order),then sap will tell me two days ahead should open a order,because three orders can be started on this work center simultaneously (32/16=2day)

if three parts needed,then 48/24=2day,is also two days ahead

so i only want system tells me the corresponding production start date or it's finish date,or whether system allows three same tasks can be started on a work center at the same time?or system need to spit it to three work centers?

so i don't know how many workers should be input in the fields of work center?

thanks in advance

helai

Message was edited by:

helai he

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

In work center go to capacity from menu select individual capacity, here enter name of workers, which 3 in numbers.Then in capacity enter no of capacities 3.

In production order select operation detail go to spliting, select splitting so that operation will get splited. Then in the next screen enter the % of work allocated among workers.

Check the above settings & revert.

Regards,

Suhas

Former Member
0 Kudos

Hi Suhas,

Are you suggesting adding Split qty. and % of work at each work center in each production order? Can you help me in setting up the same information in routing, so it will be copied every time when create the production order.

Your earliest response will be highly appreciated.

Thanks .