Hello All

I'm sorry before, my English is not good enough.

I have made my own project system report. i have problem. as i attached, i would like to merge to be one line, if project definition and network header are same. so 'Nilai kontrak/po' column and 'bobot * progress' column (as i file attached) will have sum

Accepted Solutions (0)

Answers (1)

Answers (1)

MTerence
Active Contributor
0 Kudos

Hi,

Do you mean to sum up the cost ? For Project and Network ?

Project - WBS Element - Network are Hierarchical, the cost getting posted will be settled to WBS element or Project and finally it will be settled to the cost object.

Regards

Terence