SRM Error - WBS element XXXXX budget exceeded

Former Member
0 Kudos

Hi All,

We are having issue with SRM PO not getting transferred to ECC due to error "WBS element XXXXX budget exceeded". In ECC, we have warning message set for this error however SRM is throwing hard error.

Could you please help to understand why this is happening?

Thank you,

Sunil.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Summer,

Thank you for reply.

Yes, indicator is set for Back-End Messages Displayed as Errors. However, do we have any other way to convert this error into warning message?

Thank you.

summer_wang
Contributor
0 Kudos

SRM Server
Cross-Application Basic Settings
Activate Extended Classic Scenario

Do you have flag below set on?

************
Back-End Messages Displayed as Errors
If the indicator is set, all messages output by the SAP ERP back-end after the consistency check are displayed in SAP SRM as error messages. These errors then need to be corrected before the purchase order is transmitted to the supplier. If the indicator is not set, these messages are displayed as warning messages in SAP SRM. The purchase order is replicated.

***********