Hi Expert,

Please can you suggest the standard process for the below scenerio

1. General task list is created for Planning Plant : 1001

2. Material is maintained & stocked in Plant : 1004

Unable to assign the material of Plant 1004. Giving the Error Message "Material XXXXXXX is not maintained in Plant 1001.

This error is logical as the material has not been extended to the planning plant.

If i extend the material to the planning plat my issue would be resolved, Or i can go for customization.

Is there any alternative SAP standard solution OR SAP NOTE to solve this issue without extending the material ?

Thanks,

Ranjan.

Accepted Solutions (0)

Answers (1)

Answers (1)

peter_atkin
Active Contributor
0 Kudos

https://archive.sap.com/discussions/thread/3630277

Also see BADI IWO1_TL_INTEGRATION2 via SE18