on 08-23-2007 9:12 PM
Hi Guru,
My client use MTO and have prod version 1000 & 2000. When I create SO and choose prod.version 1000, prod.order created using BOM/Routing in prod.version 1000, so the prod order cost plan.
But in costing SO, prod version 2000 is use as base in qty structure, it's mean SO plan cost is based on prod version 2000, not 1000.
How the logic of SO costing ? where config to be set in order to get SO costing based on prod version choosen.
Reward will given to any input.
Thanks
You may want to have a look at OKK5 - Quantity structure determination.(QSD)
Choose the Quantity Structure control and double click. Then click on the BOM application. In there, there is section for override alternative selection from material master. There is a check box for production version. whose help reads as
This indicator shows that, when alternatives are selected automatically according to application, the production versions maintained in the material master record are used as selection criteria.
Dependencies
<b>In the MRP view of the material master, in the requirements explosion data, the indicator for selecting alternative BOMs is maintained.
When you explode the BOM, only the alternatives for which selection by production version (2) is defined are taken into account for selection.</b>
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.