MD04 - Exception Message 20 = Cancel Process

After MRP Run through MD02. Then in MD04 screen after firming the planned order, it has an expection message 20 .

How to correct this. What are all the implecations if I convert it to production order.

With best regards,

jk

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

2 Answers

  • author's profile photo
    Former Member
    Posted on Aug 23, 2007 at 02:20 PM

    Hi Jayachandrasekhar ,

    The Exception message 20 indicates that the planned order is a unwanted one.

    As you have firmed that order system could not delete that while the MRP run.

    For any reason you need to have order leave as such, else remove the Firming indicator and run MRP again, the order will get deleted or rescheduled ( depends on the rescheduling check settings).

    Reward points if useful.

    Thanks & regards

    Mahesh

    Add comment
    10|10000 characters needed characters exceeded

  • author's profile photo
    Former Member
    Posted on Aug 23, 2007 at 02:21 PM

    Hi Jayachandra,

    System gives the message in MD04 as a error message to only alert the mrp contoller. You can ignore that.

    But in your case cancel process means that planned order is not required as already the mateiral planned order is available or stock may be there.

    The implication , you will over produce the mateiral

    You can award points on left hand side of your question if the answer is useful

    Regards

    Ranga

    Add comment
    10|10000 characters needed characters exceeded