Project Settlement

Hi,

I am doing project settlement into cost centre, but the cost from WBSelement is n't flowing into cost centre. The sequence of setlement is as fllows.

1. Production orders are settled to materials

2. Network is settled to WBSElements

3. WBSElements are settled to cost centres.

Request you to suggest to resolve the issue.

Thanks & Regards,

Biplab Ranjan

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

2 Answers

  • author's profile photo
    Former Member
    Posted on Aug 23, 2007 at 08:32 AM

    Hi,

    Can u pls check T.Code OKB9

    In this, please check whether the combinatin of cost element and profit centre giving the cost centre is maintained.

    Assign points, if found helpful.

    Regards,

    Harish

    Add comment
    10|10000 characters needed characters exceeded

  • author's profile photo
    Former Member
    Posted on Aug 23, 2007 at 12:24 PM

    Please check the settlement profile and flag the amount settlement indicator.

    Sudhir