hi sap gurus,

After i confirm a order with a final inspection confirmation(QM) ,when i check no finished goods has been shifted to unrestricted use stock(MMBE).can u suggest me how or what transaction i have go for this.In make to stock scenario

thanks

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

which insp type is activated...03 0r 04

if it is 03 then you need to perform the GR

if it is 04 you need to goto QA32 and make UD and do the stock posting from that manu.

see the help document in QM>quality inspection>insp lot complition --> stock posting and UD

Former Member
0 Kudos

Hi,

If you have with Quality inspection the inspection lot would have created go and check in the QA32 Transaction code and post the GR with making the Usuage decision.

Thanks,

Satish