Planning sequence not executed - nothing happens

Hi

we use BI IP and have transported all our settings from DEV to PRD. However in PRD none of our planning sequences react nor in the modeler nor in the workbooks. If we execute the planning sequence in the modeler nothing happens, we even do'nt get a log. In DEV we don't have problems. Anyone experienced this issue?

D

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Aug 22, 2007 at 01:14 PM

    Recheck the transport and ensure all the objects beneath the cube got transported to the prod and all the aggregation levels are active.

    Ravi Thothadri

    Add comment