Rework confirmation

Former Member
0 Kudos

Hi All,

When Iam doing confirmation for 100 pcs (yield 90,rework 10), how and where the rework qty of 10 pcs get captured ?

As I want to create the separate order for rework which I am planning to do by co01.

In my friend company, while confirming 100pcs (yield 90,rework 10), full 100 pcs is captured in stock against one batch no.111 and then manually create rework order and in BOM of that order they remove the raw materials and add the goods to be rework and any extra material needed and qty with batch no.111.

while confirming this order, it generates one more batch no.112, but this is not working in my company, can any one explain this.

Accepted Solutions (0)

Answers (5)

Answers (5)

Former Member
0 Kudos

answered

former_member204463
Active Contributor
0 Kudos

Hi Gunasekaran,

I would suggest you to go for Trigger point for the operations where the rework is probable to occur. In any case, a new order number willl be generated. But in this case, it`ll be automatically triggered. In ur example, suppose trigger point is assigned to 10th operation and when you confirm 10 pcs as rework and 90 as yield, a rework order will be generated at the background for 10 pcs.

If you donot wish to go for another order number than, assign trigger point for the operation with Insert reference operation option.

This will definitely work for you.

Reward if cleared and close the thread.

Former Member
0 Kudos

Hi Keerthi,

your trigger pt is working till the final stage but before creation of rework order, system shows a popup message for trigger pt function when I activate that it is asking for reference operation set and when I enter the ref. op. set which was created system is not accepting it gives the message as follows

"ref. op. set is not valid as per selection condition"

I checked the status, usage, lot size and unit of measure all matching with header material but I couldn't proceed , what would be the reason?

guna

Former Member
0 Kudos

Dear,

When you say rework, the system will psot 90 to to stock, for other 10 TO, we can make the system to create a secondary orders where we can settle the rework order cost to the primary order.

You can use trigger point to automatically generate the secondary order or use CORO and enter the primary production order

for more details see the link below

http://help.sap.com/saphelp_470/helpdata/en/a5/63198843a211d189410000e829fbbd/frameset.htm

and

http://help.sap.com/saphelp_470/helpdata/en/a5/63198843a211d189410000e829fbbd/frameset.htm

and

http://help.sap.com/saphelp_470/helpdata/en/a5/63198843a211d189410000e829fbbd/frameset.htm

Former Member
0 Kudos

Dear Rajesh,

CORO is for process order is there any t.code for production order and to enter primary porduction order.

guna

Former Member
0 Kudos

Logistics-->Production --> Shop Floor Control --> Order > Create> Without material.

Former Member
0 Kudos

Hi

Please check it with using

1)Trigger points and assign to particular operation. when ever the qty is rejected for rework new production order will be created with respect to the main production order.

check it this

Former Member
0 Kudos

Hi Vijay,

your trigger pt is working till the final stage but before creation of rework order, system shows a popup message for trigger pt function when I activate that it is asking for reference operation set and when I enter the ref. op. set which was created system is not accepting it gives the message as follows

"ref. op. set is not valid as per selection condition"

I checked the status, usage, lot size and unit of measure all matching with header material but I couldn't proceed , what would be the reason?

guna

Former Member
0 Kudos

Hi Gunasekaran,

What you explained in your friend company should work for you..

ie creating one more order for r/w material.

If it is not working pl let me know where you are facing this problem

You can also do the rework another way

You can add rework as an operation and post the rework time in that operation so that rework cost can be captured.

Regards

Ranga

Former Member
0 Kudos

Hi ranganathan,

My problem is not creating rework order but when I comfirm 90 pcs as yield and 10 pcs as rework (my friend's company) my stock is showing 100 pcs against one batch no. instead of 90 how it is possible.

guna

Former Member
0 Kudos

Hi Guna,

You should maintain different storage location for rework.

I think you are maintaining same storage location. can you check it?

Regards

Rangs