on 08-22-2007 11:20 AM
Hi,
Can any one tell me about various production confirmations.
1. CO11N - Time ticket
2. CO19 - Time event -> What about the qty to be confrimed?
3. CO1F - Progress
4. CO15 - For order -> What about the operations confirmation?
Can anyone explain me about the different confirmations in detail
Thanks in advance
Please go through the help document given below
http://help.sap.com/saphelp_470/helpdata/en/a5/63198843a211d189410000e829fbbd/frameset.htm
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Could you plse elobrate me about Time event, Confirmation at order level,
In Time event, example if i do confirmation for setup
Example 1:
1. Setup start - 22.08.2007 - 10.00am
2. Setup finish - 22.08.2007 - 11.00am.Will it consider the 60mins time for setup activity automatically??
Example 2:
1. Setup start - 22.08.2007 - 10.00am
2. Setup interupt - 22.08.2007 - 10.30am
3. Setup start(again) - 22.08.2007 - 11.00am
4. Setup finish - 22.08.2007 - 11.30am. Will it consider 60mins time for setup activity automatically?
What about the quantity confirmation in Time event confirmation.
Same way Confirmation at order level
If i confirm at order level, what abt the operaiton qty and activity consumption.
Will it take planned activites as actual??
User | Count |
---|---|
100 | |
11 | |
11 | |
6 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.