Process chains

I have done some modifications to the process chains.Now ,got to test them.But ,the loads fail quite often.Its got to do with some dependencies.I am loading transaction data.But ,Prior to this Master data loads must be triggered using the chains.I think these are dependencies.So,I want to know how these dependencies can be identified for a particular process chain.Please give some information as i am new to this proj. and i have to start work immediately

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    avatar image
    Former Member
    Aug 22, 2007 at 10:07 AM

    Poonam,

    You can know the dependencies from load failures and what the log says. As you said, if master data needs to be loaded first, the load will fail saying something related to this. Like that you can analyze what should be done for the load to succeed. You can get inputs from others regarding the loading sequence....

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Poonam,

      You should get that information form the ones who worked on that earlier. That is the first thing. You must be having some SOP's documented. Else you should check all teh data sources and come to a conclusion....

  • avatar image
    Former Member
    Aug 22, 2007 at 03:23 PM

    One way to find out the dependencies is to open the Transaction DataSource and see what objects it is extracting...then all you need to do is make sure that you load the master data for those objects prior to running the transaction load. Good luck.