dear all:

i have a problem when i using ck24.

details of this problem:

1.i have already made standard cost estimates using tcode ck11n successfully.

2.when i updated price using tcode ck24,there is a error message.

it is : company code 1000

the start of period 011 is 2007-11-01,which was not yet been reached ,only

cost estimates from the current priend can be released.

my period is November and December .

i want to open the period of august or September using tcode MMRV.

but it is not be allowed.

so i want to how to open the period of august or September .

if not ,i can't update price using tcode ck24.

thank you.

best regards!

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

Change the costing date periods

From period - u say start of the period

It will create cost estimate from the beginning of Aug. Mark it, when u do so it updates the future std cost in costing 2 view

Then in Nov u can release the cost

U cannot open seot until aug is closed and all MM transactions are completed.

Hope the above clarifies - pls assign points

Answers (2)

Answers (2)

Former Member
0 Kudos

hi

i have solved my problem.

i initialized the mm period through tcode mmpi.

best regards!

Former Member
0 Kudos

dear Sreedhar:

i can't catch your mean!

how to release the cost in nov. after ck11n?

please tell me the details!

thanks for your reply.

best regards!