on 08-22-2007 10:19 AM
Dear all,
In "Define Confirmation Parameters" (OPK4) under "checks for overdelivery" we have maintained "overdelivery tolerance is not checked". But when I do GR (in MIGO or MB31) for a quantity which exceeds the order quantity (say order qty is 10 & I am doing GR for 11), the system does not allow GR.
I do not want to maintain overdelivery tolerance in WS view of material master.
Please help
Sameer
Dear Sameer,
OPK4 settings is effective for confirmations and not for GR. Either u maintain the overdelivery tolerance in the WS view which is valid for GR other wise maintain the same in the relevant production order Goods receipt tab. Hence it will be valid only for that production order.
reg
Kiki
Award points if this helps
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sameer,
You can maintain this in prodn order >> goods receipt tab..
Regards,
Ranga
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Sameer,
What is maintained in confirmation parameters is valid for checking the "Yield" quantity which is entered during confirmation, whereas materail GR tolerance is controlled by what is defined in Work Scheduling view only.
Can you please let us know why you do not want to maintain in WS view?
Regards,
Prasobh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
7 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.