Capacity planning result for key resource in LTP

I want the capacity planning for key resource in long term planning in inactive mode.What are the steps required for it.

Regards,

Sunil

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Aug 22, 2007 at 09:13 AM

    Hello Mr Sunil

    Use T code CR02. Enter required work center

    Go to capacity header view & remove the tick mark in the check box againt "long term plannig"

    But can can you pl tell us the logic behind this requirement of not considering a critical resource in LTP.?

    Regards,

    Ramasamy