PO not going in account of release authority.

Former Member
0 Kudos

Hi all

In my release strategy for POs, Porg, net order value and Material Group are defined as a chracteristics. while creating PO with multiple lines with multiple Material Groups it is going to incorrect release authority. that is picking another release strategy. i m checking properly in PRD AND DEV Servers. in DEV Server it is working properly. why it is not working in PRD Sever.can any one suggest the solution to this?

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

If both the strategies are having the same blank value in material group characterstic, then based on other characterstic values system proposes the release strategy. check the charcterstic values in the PO and release strategy, if both strategies are applicable, then system proposes the first one it gets in the table.

Regards,

Ramakrishna

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi,

I am not understand why you put up the release stratezy at material group level because material group is on item level. As PO has been released fully not on item level basis.Instead of placing the release stratezy at item level,why not you put it only on header level.cause no where you release the PO at item level. But it will create only confusion for picking the release stratezy.you can put release stratezy on one more char. i.e. Incoterm(header level).

So please convey your client to put release stratezy only on header level.

Thanx

Former Member
0 Kudos

hi rama krishna,

thanks for ur solution. blank option is ticked in both release strategeis but the another release strategy is placed before the correct one. is this the reason for picking another release strategy.

regards

Siva

Former Member
0 Kudos

Hi,

The material group is a item level charcterstic. If you use a item level charcterstic and the PO has different values for material groups, it checks for a strategy with material group as blank value. check in your release strategy, value assignment whether any strategy is having blank as value for the material group charcterstic.

Also check in CL20N in production system, the required relase group and strategy status is 1 (released).

Regards,

Ramakrishna