08-22-2007 2:05 AM
Hi all,
How to schedule a background job for the first 5 days of the month to run monthly?
Thanks!
08-22-2007 2:17 AM
In trnsaction SM36 while defining the background job -> Start condition -> Date/ time. Here u can specify start & end time. Goto 'Period values' .Here u can specify the time interval
Check the below link for more information:
http://help.sap.com/saphelp_erp2005vp/helpdata/en/ef/2c513897110872e10000009b38f889/frameset.htm
Thanks
Seshu
08-22-2007 2:17 AM
In trnsaction SM36 while defining the background job -> Start condition -> Date/ time. Here u can specify start & end time. Goto 'Period values' .Here u can specify the time interval
Check the below link for more information:
http://help.sap.com/saphelp_erp2005vp/helpdata/en/ef/2c513897110872e10000009b38f889/frameset.htm
Thanks
Seshu
08-22-2007 2:35 AM
Hi,
I had also similar scenario. I need to schedule a job last but one day previous of every month.
<i>May be my solution will not in a proper way</i>
I have written wrapper program and inside the program i called the program after checking the sy-datum is 1 day less than end day of the month.
Then i schedule the wrapper program schedule to run every day.
aRs
09-12-2007 6:44 AM
09-12-2007 6:45 AM
Created 5 jobs and scheduled each monthly. Thanks for the responses.