Skip to Content
avatar image
Former Member

Sale Order Status after dellivery of materials from Projects

Hi,

I have ETO sccenario which consists of all modules such as SD,PS.PP etc. Materials will be procured from external vendors & manufactured inhouse through project systems. After delivery of materials from project systems, billing & invoicing will be done at sales level.

On delivery of materials from projects, sale order status remain open. Request you to look into the matter & suggest about status change of sale order after delivery / billing.

Thank you in advance.

Regards,

Ranjan

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Aug 22, 2007 at 07:37 AM

    I am not understanding your issue Biplab...when you have delivered the material through PS...then from where did the Sales Order incomplete status came up...are you entering the WBS element in the SO..please specify your problem.

    Regards,

    N

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi,

      In sale order, WBSE is assigned. Delivery of materials are through cns0. then subsequently picking / packing / billing will happen at sales level. Billing is of delivery related. Please suggest to fix the issue.

      Thanks & Regards,

      Biplab Ranjan