Skip to Content
avatar image
Former Member

Factoring top urgent

HI All,

Our payroll calculation is for 26 days a month, In PCR : INP1

I am using this rule

/802 Partial period factor 2

RTE=TASOLL Set

RTE-TAAU** Subtraction

RTE*KGENAU Multiplication

RTE/TADIVI Division

ADDWT * OT Output table

But this rule is for "Work Days"

Please suggest. how do we go further

Thanks

Veer

Message was edited by:

veeresh G R

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Best Answer
    avatar image
    Former Member
    Aug 22, 2007 at 03:20 AM

    Haii..

    RTE = TKSOLL

    RTE - TKAU**

    RTE*KGENAU

    RTE/TKDIVI..

    ADDWT *.

    Make sure to maintain the constants in the repective tables...

    manu

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Aug 22, 2007 at 03:05 AM

    Hai

    pls change the rate as tksoll

    RTE = TKSOLL

    Desired result will be obtained..

    Manohar

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Ram,

      As you said I have made the change like this but it is giving a wrong calculation

      /802 Partial period factor 2

      RTE=TKSOLL Set

      RTE-TAAU** Subtraction

      RTE*KGENAU Multiplication

      RTE/TADIVI Division

      ADDWT * OT Output table

      Thanks

      Veer

  • avatar image
    Former Member
    Aug 22, 2007 at 10:22 AM

    Hi, Please do not specify any constant in RTE=; instead use any of the following operations to get your desired result. If you specify any constant against RTE it might not give you desired result in your retro calculation

    Here is some information that might be useful. The same is available in SAP documentation

    Planned working time in accordance with the employee's personal

    schedule totalled over the basic pay periods in the payroll peri

    KSOLL : Planned working time in calendar days

    ASOLL : Planned working time in working days

    SSOLL : Planned working time in working hours

    Total working time in the payroll period in accordance with the

    employee's personal work schedule totalled over the basic pay

    periods in the payroll period

    KDIVI : Total working time in calendar days

    ADIVI : Total working time in working days

    SDIVI : Total working time in working hours

    For a calculation example, see Calculation Example for xDIVI

    Total working time in the payroll period (lump sum) KDIVP : Tota

    working time in calendar days ADIVP : Total working time in work

    days SDIVP : Total working time in working hours

    The values KDIVP and ADIVP are taken from the Payroll Constan

    table (T510H); the value SDIVP is the employee's basic pay

    divisor (from field DIVGV in infotype P0008). The values are

    those valid at the end of the last basic pay period.

    Total working hours in the payroll period according to the

    employee's personal shift schedule totalled over the basic pay

    period and for a certain weekday.

    KWKDx : Total working time in calendar days

    AWKDx : Total working time in working days

    Regards

    Judith

    Add comment
    10|10000 characters needed characters exceeded