Dear Gurus,

We have read some threads about vendor synchronization, but we still have some doubts about the strategy of the synchronization.

Can anybody tell us how are you managing with this topic? I mean:

1- how do you perform the initial load of vendors in SRM?

2- how do you keep them update?

3- What´s the use of BBP_VENDOR_SYNC ? Create of only update?

Now we are performing the initial load with transaction BBPGETVD but this transaction can not be used for all vendors. And if we run report BBP_VENDOR_SYNC no vendor is synchronized.

Thanks for the help!!!!

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    avatar image
    Former Member
    Aug 21, 2007 at 01:33 PM

    Hi

    <b>Please go through the links -></b>

    Note 1029497 - BBP_VENDOR_SYNC: vendors cannot be updated

    Note 953682 - BBP_VENDOR_SYNC: Vendor replication

    Note 823629 - EBP Vendor Replication from R/3 BBP_VENDOR_SYNC

    different-programs-for-vendor-update

    difference-between-bbpupdvd-bbpvendorsync

    bbpvendorsync-versus-bbpgetvd

    vendor-replication-problem

    Regards

    - Atul

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Aug 21, 2007 at 01:51 PM

    Issue Resolved! thank! I tried to perform the synchronization and worked successfully! I assigned points.