Hi Gurus
We have one FG (REM) and have one Raw Material as bom component inside it.
System not generating pull list for the FG against Planned Order (REM)
Need your inputs
K.Prabakaran
Dear Mr.Prabhakaran,
Please check with this,
1.Staging Types - Check whether tick mark against the check box for Storage
Location Level & also remove the requirements date field.
2.Under Global Settings - Remove the tick mark for chack box against Include All
requirements & include the tick mark for all the other check boxes.
3.Check whether Production storage location mentioned for your item in MRP2
view is also present in MMSC,if not include and save the datas.
4.Also if already sufficient amount(quantity) of that particular raw mateiral exists in
your production storgae location (header material),then also the system does not
shows you any Replenishment elements.
Check with this & revert back to forums if still the problem exists.
<u>Reward points if useful.</u>
Regards
Mangal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.