Material Under Quality - Block for invoice/payment

Dear all,

When the material is lying under quality inspection the user should not be able to do invoice posting or posting.By standard its allowing once GR is done.How to do this

Regards,

Milton.I

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

4 Answers

  • avatar image
    Former Member
    Aug 21, 2007 at 11:07 AM

    Hi Vijay,

    Please check the following parameters of PO line item details screen,

    GR

    GR non-val

    IR

    GR-based IV

    Stock type

    Regards,

    MBKM

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Aug 21, 2007 at 11:13 AM

    Hi Vijay,

    You need to set this message number 280 for message class M8 as error message, then system will not allow you to post the invoice if the material is in quality inspection.

    So define this IMG settings in Logistics invoice verification ---system messages and if not include this message number 280 as error message.

    your problem will be solved.

    rgds

    Chidanand

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Dear Vijay,

      There was similar requirement from my client for the same. At that time contacted the OSS.

      The message no.280 is there but you can not configure it.

      Not allowing to post the external document like Invoice as it comes leads to so much descripency in real time.

      The best solution what SAP has given is in QM control key just tick the Invoice and when the invoice of that perticular material comes for posting you can post but that will be blocked for the payment if the material is not cleared from the Quality.

      As the material cleared from Quality, you can release the Invoices and if the material is rejected can raise the credit memo.

      This is what we did after consulting the OSS

      Thanks And Regards,

      Krishna Reddy

  • avatar image
    Former Member
    Aug 21, 2007 at 11:34 AM

    The following actions are required

    <b>1. In customizing</b>

    QM in Logistics --> QM in Procurement --> Define control Keys

    Define a control key (if required) by enabling block invoice in the QM control in procurement tab. - maintain a short text to identify this control key.

    <b>2. In Material Master</b> - Quality Management view, in the Procurement data tab, call this QM control key. Also enable QM in procurement active.

    Doing this for the identified material in the material master, the invoice against this material will always be in block status as long as the material is in Quality Inspection.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Aug 21, 2007 at 11:56 AM

    Hi,

    Please use the QM control key 0007( delivery release, invoice block) in the quality view of material master under procurement data.

    then you will be able to block the invoice.

    Please check the scenario in your DV server. It will definitely work.

    Thanx